This Subcontractor Agreement is made on October 17, 2026 between Your Company ("Contractor"), the general contractor, and Your Client ("Subcontractor").
Subcontractor will perform the [trade, for example: electrical] work described in its proposal dated [date of the proposal, for example: April 9, 2026] and shown in the project plans, both part of this agreement, for [the project, for example: the kitchen remodel at 14 Elm Street] (the "Project"). Subcontractor provides all labor, materials, tools, and equipment for its work unless the proposal says otherwise.
The subcontract price is $5,200, billed by this schedule of values:
Before starting work, Subcontractor will give Contractor certificates of insurance showing general liability coverage of at least $1,000,000 per occurrence and $2,000,000 in total, commercial auto coverage, and workers' compensation as the law requires. Subcontractor will name Contractor as an additional insured on its general liability policy, and keep this coverage in force until its work is complete.
Subcontractor will hold the licenses its trade requires, obtain any trade permits the work needs, and perform its work to the codes that apply and to pass inspection.
Subcontractor is responsible for the safety of its own workers and work, will follow the safety rules that apply and Contractor's site rules, and will report any accident or hazard to Contractor right away.
Subcontractor will perform its work on the schedule Contractor sets, coordinate with other trades on site, and attend coordination meetings when asked. Subcontractor will tell Contractor promptly of anything that may delay its work.
Subcontractor will keep its work area clean each day and remove its own debris and leftover materials.
Subcontractor won't perform extra or changed work without a written change order signed by Contractor that states the change, its price, and its effect on the schedule.
Subcontractor warrants its work against defects in materials and workmanship for one year from completion of the Project, and will correct any defect promptly at no charge.
Each party will defend and indemnify the other against claims for injury or property damage to the extent caused by its own negligence, or that of its employees or subcontractors.
Subcontractor is an independent contractor. It controls how its work is done and is responsible for its own workers, taxes, and benefits.
This agreement is governed by the laws of [state, for example: Oregon]. It, Subcontractor's proposal, and the project plans are the entire agreement between the parties, and may only be changed in writing. Subcontractor may not assign it or subcontract its work without Contractor's written consent. If any part is found unenforceable, the rest remains in effect.
By signing below, both parties agree to these terms.