The full template
Words in brackets, like [Client Name], fill in automatically from your client's details when you use the template in Clientary.
In the editor, you can change any section or add your own. Once you send it, your client signs online from any device. Edit this template online
This Change Order is made on [Contract Date] between [Company Name] ("Contractor") and [Client Name] ("Owner"). It changes the Construction Contract between them dated [date of the contract, for example: April 6, 2026], with an original contract price of $62,500 (the "Contract").
1. The Change
Contractor will add LED under-cabinet lighting along all upper cabinets, on a dimmer switch, and two additional GFCI countertop outlets on the island side of the kitchen.
2. Reason
Requested by Owner during the electrical rough-in, so the new wiring can be run before the walls are closed.
3. Cost
- Materials, including LED strips, drivers, dimmer, outlets, and wire: $640
- Electrician labor, 8 hours at $95: $760
- Drywall patch and paint touch-up: $220
- Overhead and profit, 10%: $162
- Total for this change: $1,782
4. Schedule
This change adds 2 working days to the schedule in the Contract.
5. Contract Price
- Original contract price: $62,500
- Previous change orders: $0
- This change order: $1,782
- New contract price: $64,282
The cost of this change is billed with the next draw after the work is done.
6. Everything Else Stays the Same
All other terms of the Contract remain in effect and apply to this change. Once signed by both parties, this change order becomes part of the Contract. Contractor will begin the changed work when it receives Owner's signature.
By signing below, both parties agree to this change, its price, and its effect on the schedule.
How to use this template in Clientary
- Edit it online. Change any section or add your own. No account needed.
- Preview it as your client will see it. Fill in who it's for and pick a design.
- Start your free trial to send it. Confirm you'll have it reviewed, since templates aren't legal advice, and your contract is waiting in your new account with your client's details filled in.
- Send it to be signed. Your client reviews and signs online, and you can see when it's viewed and signed.
Learn more about contracts and e-signatures in Clientary.